Which term describes the process of presenting a change to the contractor who will quote a price?

Presenting a proposed change to the contractor so they can provide a price is a Proposal Request. It clearly lays out the change, references the existing drawings and specs, and asks the contractor to submit a price proposal (and any schedule impacts). This keeps the pricing process separate from the design decision, allowing formal evaluation and negotiation of the cost. A Construction Change Directive is used when the owner wants the work changed and authorized to proceed before a price is agreed, often due to time pressure. A site survey is just assessing the current conditions on site, and O&M relates to operations and maintenance activities.

Presenting a proposed change to the contractor so they can provide a price is a Proposal Request. It clearly lays out the change, references the existing drawings and specs, and asks the contractor to submit a price proposal (and any schedule impacts). This keeps the pricing process separate from the design decision, allowing formal evaluation and negotiation of the cost.

A Construction Change Directive is used when the owner wants the work changed and authorized to proceed before a price is agreed, often due to time pressure. A site survey is just assessing the current conditions on site, and O&M relates to operations and maintenance activities.